The Universal Concrete Formula

Whether you're pouring a driveway, a backyard patio, a sidewalk, or a foundation slab, the formula for calculating concrete is identical. Concrete is measured and ordered in cubic yards in the United States. Here is the complete process:

The Formula

Cubic Yards = (Length × Width × Thickness in feet) ÷ 27

Since thickness is usually measured in inches, convert it first: Thickness in feet = Thickness in inches ÷ 12

Standard Concrete Thickness by Project Type

One of the most common mistakes homeowners make is pouring concrete that is too thin. The correct thickness depends on what loads the slab will carry:

Project Type Recommended Thickness Notes
Sidewalk / walkway4 inchesFoot traffic only
Patio (foot traffic)4 inchesFurniture and BBQ grills
Residential driveway (passenger cars)4–5 inchesNo trucks or RVs
Driveway (SUVs, light trucks)5–6 inchesHeavier personal vehicles
Heavy vehicle / RV pad6–8 inchesDelivery trucks, campers
Garage floor slab4–6 inchesRebar required at 4 inches
Foundation / footing8–12 inchesStructural — engineer required

Worked Examples

Example 1: Standard 2-Car Driveway

Dimensions: 20 ft wide × 40 ft long at 5 inches thick.

  1. Convert thickness: 5 ÷ 12 = 0.417 ft
  2. Cubic feet: 20 × 40 × 0.417 = 333.6 cu ft
  3. Cubic yards: 333.6 ÷ 27 = 12.36 cu yd
  4. Add 10% waste: 12.36 × 1.10 = 13.6 cu yd → order 14 yards

Example 2: Backyard Patio

Dimensions: 16 ft × 24 ft at 4 inches thick.

  1. Convert thickness: 4 ÷ 12 = 0.333 ft
  2. Cubic feet: 16 × 24 × 0.333 = 127.9 cu ft
  3. Cubic yards: 127.9 ÷ 27 = 4.74 cu yd
  4. Add 10% waste: 4.74 × 1.10 = 5.2 cu yd → order 5.5 yards

Example 3: Sidewalk

Dimensions: 60 ft long × 4 ft wide at 4 inches thick.

  1. 60 × 4 × 0.333 = 79.9 cu ft ÷ 27 = 2.96 cu yd
  2. Add 10%: 2.96 × 1.10 = 3.26 → order 3.5 yards

Ready-Mix Truck vs. Pre-Mixed Bags: Which Is Better?

Method Best For Cost Range Minimum Order
Ready-Mix TruckProjects over 1 yard$125–$165 per cubic yard1 yard (short-load fees apply)
80 lb Bags (0.60 cu ft each)Projects under 1 yard$5–$8 per bag ($225–$360/yard)None

For projects over 1 cubic yard, ready-mix concrete is almost always cheaper per cubic yard than mixing bags. The crossover point is approximately 30–45 bags (1 cubic yard). Above that, order a truck. Below that, bags are more convenient.

How Many Bags Do You Need?

Project Volume 80 lb Bags Needed Recommendation
0.5 cubic yards~23 bagsUse bags
1 cubic yard~45 bagsBags or smallest truck order
3 cubic yards~135 bags (not practical)Order ready-mix
10+ cubic yardsNot feasibleReady-mix only

Control Joints: The Key to Crack-Free Concrete

No concrete slab is crack-free — but you can control where the cracks occur by cutting control joints (also called contraction joints) into the surface. These are intentional weakened planes that guide cracking to predictable, neat lines. The rule of thumb for joint spacing:

  • Joint spacing (feet) = 2–3 × slab thickness (inches). For a 4-inch slab: joints every 8–12 feet. For a 5-inch slab: joints every 10–15 feet.
  • Joints should be cut to a depth of at least 1/4 the slab thickness. For 4-inch slab, cut joints at least 1 inch deep.
  • Cut joints within 6–12 hours of finishing while the concrete is still green (not fully cured).

Use our free Concrete Calculator to get instant cubic yard calculations, bag counts, and cost estimates for any slab, driveway, or sidewalk project.